Heritage School Bond Update
Heritage School Additions
Summer 2026
Groundbreaking on the new additions is scheduled for May 28, 2026 with actual construction to start June 8, 2026. During phase one, electrical, plumbing, and heating infrastructure will be completed to the new additions during the summer of 2026. Foundations, block work, windows, roofing and the new additions should be weather-tight before winter. Classroom HVAC units and roofing air conditioners are scheduled to be replaced during the summer of 2026.
Fall 2026
Construction will continue during the school year inside the additions. Student learning will not be impacted, however, parent & staff parking may be impacted at times.
Summer 2027
Interior remodeling work will begin Summer, 2027 in the art room and interior corridors connecting to the new additions. We expect to open the new classrooms in August of 2027.
Projects Completed
- Camera/Guest Security System Upgrades - Completed Summer 2023
- New inclusive playground equipment and a new turf field- Completed Summer 2024
- Soft playground surfacing and playground structures installed- Completed Summer 2024
- Upgraded classroom technology- Completed Summer 2025